Barack Obama was elected U.S. President in November 2008, and in February 2009 Congress passed and Obama signed the American Recovery and Reinvestment Act of 2009 (ARRA) which included $8 B for infrastructure improvements to intercity rail with priority for HSR projects. On Qctober 1, 2009, the CHSR Authority submitted six application for federal funding under this program, two for planning and four for ifrastructure projects:
- NEPA/CEQA for Phase 2: Merced-Sacramento & L.A.-San Diego ... $60.0 million
- NEPA/CEQA for Altamont Corridor ... $22.5 M
- Complete design and construction of 50-mile segment, San Francisco-San Jose ... $980.0 M
- Complete design and construction of 50-mile segment, Merced-Fresno ... $466.0 M
- Complete design and construction of 98-mile segment, Fresno-Bakersfield ... $819.5 M
- Complete design and construction of of 30-mile segment, L.A.-Anaheim ... $2,187.5 M
The Grant Agreement for the initial ARRA award for $2.47 B was signed in December 2010 (increased to $2.55 B in August 2011), and the agreement for the "2010" award for $929 M was signed in November 2011. In the meantime, there were extensive negotiations about the scope of the work, complicated by a growing realization that CHSRA had woefully underestimated construction costs in its 2005 program-level EIR which the application was based on. It was in the interest of both CHSRA and USDOT to build the longest possible segment, and they settled on Madera-Shafter, some 119 miles, pegged at a cost of $5.8 B with CHSRA absorbing any additional costs. USDOT recognized that full HSR operations on this segment were not feasible until connected to a larger system, so non-electric San Joaquin service on the CVS was accepted as a satisfactory interim alternative. With construction of this segment now half complete, the cost is currently estimated at $12.4 B, relying on an additional state contribution of some $7 B from Greenhouse Gas Cap & Trade revenues.
Completion date for the ARRA award was originally Sept. 30, 2017, later extended to Dec. 31, 2022, although the federal grant still had to be spent before the first date. Completion date for the "2010" award was originally Dec. 31, 2018, later also extended to Dec. 31, 2022. USDOT allowed CHSRA to spend ARRA funds in advance of the local match, unusual for a grant of this nature, but this leniency was not extended to the "2010" award. In May 2019 none of this grant had yet been spent, and the Trump administration formally withdrew the award.
References
- American Recovery and Reinvestment Act’s (ARRA) High-Speed Intercity Passenger Rail Program (HSIPR) Application, California High-Speed Rail Authority (2009).
- Funding Agreements, California High-Speed Rail Authority (2010, 2011).
No comments:
Post a Comment