This post appears in the RailPAC Weekly E-Newsletter, July 30, 2012.
California can complete the North-South spine of its HSR project by 2030 without voter approval of further State bonds, but only if it completely revamps the system currently being pursued by the CHSR Authority. The Authority has chosen an extremely bad route, which is longer, slower, and vastly more expensive than the direct route via Tejon and Altamont passes.
Proceeding beyond the first segment from Madera to Bakersfield, the next step is to complete an initial operating segment (IOS) by building the second segment southward, from Bakersfield to Los Angeles via Tejon pass. The cost of this segment, based on the 2005 EIR, is around $10 billion in addition to the $6 billion being spent on the first segment. With 50% federal support, the State would have to draw an additional $5 billion from Prop 1A bonds. Ideally, the IOS should be extended to Anaheim as inexpensively as possible, using dedicated tracks in a rebuilt (and fully grade separated) Metrolink right of way.
Building the IOS would use up nearly all of the Prop 1A bonds, and other sources of support are needed to continue construction northward. Fortunately, the IOS (and successive extensions) are expected to generate significant net income from fares, sufficient to support well over $5 billion in revenue bonds. Together with federal grants, another $10 to $15 billion in additional construction is possible. This will cover the cost of the section from Madera to Oakland via Altamont pass, estimated to be $10 billion in the 2005 EIR. This will complete the spine of the HSR project, running from Oakland to Anaheim. The total cost is well under $30 billion (current dollars).
Once the spine is operational, branches to San Jose, Sacramento, and Riverside, and an extension to downtown San Francisco can be built when justified and financing is available. But it is premature to do detailed planning for these extensions, since their construction cannot possibly occur until after 2030. Furthermore, most of the extensions can be built at standards far below the 220 mph design speed for the spine, and may even involve track sharing with high performance local rail service.
Comparisons of proposed spine (including an extension to S.F.) with the CHSR Authority's current plan:
Distance (LA-SF): 420 miles vs. 450 miles
Run time (LA-SF): 2:17 vs. 2:38
Capital cost (LA-SF): $32 B vs. $62 B (!!!)
References:
Final Program EIR/EIS Report: Volume 3: Appendix 4-C, "Capital Cost: High Speed Train Alternative" (CHSR Authority, 2005)
Revised 2012 Business Plan Source Documents: "Cost Changes from 2009 Report to 2012 Business Plan" (CHSR Authority, 2012)
Comment by Noel Braymer, Newsletter editor:I don't think that the current plan by the California High Speed Rail Authority is written in stone and I expect more changes will happen to it over the years. RailPAC's priority now is to push for a new rail connection between Palmdale and Bakersfield and get passenger rail service between Southern California, the San Joaquin Valley and the Bay Area in the next few years. It is unlikely that the Tejon Pass will be used for rail service in the near future. ACE is planning to expand service between Merced and San Jose in the next 5 years over the Altamont Pass to connect with the San Joaquins. Few details are available of what route or how frequent the service will be for the new Altamont pass ACE service.