Note: Financial data presented here (Tables 1-3) are drawn mainly from financial reports to the CHSR Finance & Audit Committee at its July 2020 meeting (scheduled but then canceled).
The California HSR project currently has enough money in the bank and in the pipeline from expected Prop 1A bond sales and Cap & Trade auctions that it isn't going to have a cash flow problem for at least five years. Its immediate problem is a slow pace of construction which is inadequate to meet established completion dates, particularly the Dec. 31, 2022, deadline for satisfying the federal funding agreement for completing the Central Valley Segment (Madera to Shafter). Work on thus segment has been underway for some five years, but it is only half completed with $5.2 billion expended so far and $6.5 B remaining in the budget (see Table 1). The current pace of construction is about $1 B per year (Table 2), so it is unrealistic to expect completion of the CVS before the end of 2025.
Current work on the CHSR Project includes construction of the CVS, a modest amount of work on the "bookends" (improvements to Caltrain and run-through tracks at LAUS), and completion of a full set of project-level EIRs for the entire Phase I, from San Francisco to Anaheim. CHSRA estimates the total cost of the current program at $14.7 B (Table 1), but adds "Other Costs" to reach a total of $15.6 B in the 2020 Draft Business Plan (Exhibit 3.4, p. 66). Some $6.7 B had been spent by May 31, 2020, according to the accounting in Table 1. About $8 B is budgeted to complete the current program, with a nominal completion date by the end of 2022 as specified by the federal Grant Agreement, but this deadline will not be met. CHSRA has only $2.6 B cash in hand (Table 3) with about $1.9 B expected from Cap & Trade, leaving it some $2.5 B short.
In 2019 Gov. Newsom set a specific goal for CHSR, to complete the entire CVS from Merced to Bakersfield (170 miles) before starting work on the Pachaco pass route to Gilroy and San Jose. The estimated cost for the entire CVS is $20.4 B (Business Plan, Exhibit 3.4), or $4.8 on top of the $8 B needed to complete the first 119 miles for a total remaining outlay of nearly $13 B to finish the entire CVS, from Merced to Bakersfield. Authorized funding throuh tht end of 2030 includes $2.6 B in the bank plus 10.5 years of Cap & Trade revenue at about $750 M per year, or $7.9 B, for a total of some $10.5 B. There is a $2.5 B shortfall, barring unexpected additional support.
What's the future for HSR in California?
The obvious short term goal is to complete the CVS (119 miles) without electrification, to fulfill the federal agreement; this would reduce travel time for the existing San Joaquin service by one-hour. The CHSRA appears committed to the North Initial Operational Segment (IOS), alias "Valley-to-Valley", from Bakersfield to San Jose, but this will require a major infusion of state funding which the legislature is unlikely to approve. The Early Train Operator (ETO) proposed completing the entire CVS (170 miles) including electrification, with diesel-powered feeder service from the north connecting to HSR at Merced. This would require an investment of some $10 B in additional funding in the San Joaquin and Altamont Corridor Express (ACE), including major improvement to Altamont Pass, to make it effective. IOS North is even more expensive, reqiring another $16 B in addition to the entire CVS.
The question of how to effectively use a stand-alone CVS -- either 119 or 170 miles -- is tied into the larger issue of the role HSR should play in expanding intercity rail service in California. The present State Rail Plan (2018) was prepared under the auspices of the previous Governor who was thoroughly committed to the current HSR Project, which depreciated the value of the existing corridors ("Amtrak California") and deferred major improvements to them until HSR Phase 1 was completed. Discussion of a better balanced plan will be covered in a subsequent post on this blog.
Table 1. Expended and Available Funds for California HSR
|
Author-ized |
Appropri-ated |
Program Budger |
Expended To Date |
Percent Expended |
| Project Development |
| Bond Fund (Prop 1A) |
$0.900 |
$0.575 |
$0.575 |
$0.494 |
86% |
| Cap and Trade |
$0.678 |
$0.678 |
$0.618 |
$0.160 |
26% |
| Federal Trust Fund (ARRA) |
$0.511 |
$0.511 |
$0.487 |
$0.487 |
100% |
| Subtotal, Project Develop. |
$2.089 |
$1.764 |
$1.681 |
$1.142 |
68% |
| Construction |
| Bond Fund (Prop 1A) |
$7.000 |
$2.609 |
$2.609 |
$2.4774 |
95% |
| Cap and Trade |
$10.498 |
$10.498 |
$7.037 |
$0.699 |
10% |
| Federal Trust Fund (ARRA) |
$2.1141 |
$2.114 |
$2.060 |
$2.060 |
100% |
| Subtotal, Construction |
$19.612 |
$15.221 |
$11.705 |
$5.235 |
45% |
| Bookend Projects (Local Assistance) |
| Bond Fund (Prop 1A) |
$1.100 |
$1.100 |
$1.100 |
$0.153 |
14% |
| Cap and Trade |
$0.198 |
$0.198 |
$0.198 |
$0.168 |
85% |
| Subtotal, Bookend Projects |
$1.2981 |
$1.298 |
$1.298 |
$0.320 |
25% |
| Subtotals by source of support |
| Bond Fund (Prop 1A) |
$9.000 |
$4.284 |
$4.284 |
$3.124 |
73% |
| Cap and Trade |
$11.374 |
$11.374 |
$7.853 |
$1.027 |
13% |
| Federal Trust Fund (ARRA) |
$2.625 |
$2.625 |
$2.547 |
$2.547 |
100% |
| TOTAL |
$22.999 |
$18.283 |
$14.684 |
$6.700 |
46% |
Table 2. Cumulative Program Totals for California HSR
|
Total to 6/30 2014 |
FY 14-15 |
FY 15-16 |
FY 16-17 |
FY 17-18 |
FY 18-19 |
FY 19-20 |
Total to 6/30 2020 |
| California Financial Support |
| Prop 1A |
$400 |
$45 |
$56 |
$1,323 |
$800 |
$600 |
$390 |
$3,614 |
| Cap & Trade |
--- |
$650 |
$459 |
$221 |
$708 |
$787 |
$489 |
$3,313 |
| Expenses by Category |
| Administrative |
$103 |
$17 |
$21 |
$22 |
$19 |
$21 |
$26 |
$229 |
| Project Delivery |
$11 |
$8 |
$11 |
$13 |
$16 |
$17 |
$19 |
$94 |
| Local Assist. |
--- |
--- |
--- |
--- |
$0 |
$92 |
$99 |
$191 |
| Proj. Develop. |
$498 |
$46 |
$134 |
$179 |
$145 |
$86 |
$84 |
$1,171 |
| Construction |
$227 |
$430 |
$879 |
$922 |
$1,016 |
$765 |
$1,400 |
$5,639 |
| TOTAL |
$838 |
$501 |
$1,044 |
$1,135 |
$1,197 |
$981 |
$1,628 |
$7,325 |
Table 3. California Financial Support for HSR
|
Prop 1A Bond Fund |
Cap & Trade |
| Revenue |
$3,614 |
$3,313 |
| Expenditures |
$3.124 |
$1.027 |
| Difference, Revenue minus Expenditures |
$490 |
$2,286 |
| Cash Balance, May 30, 2020 |
$288 |
$2,383 |