The current California HSR plan has significant flaws; a major mistake was selecting a detour via Palmdale instead of the direct route via I-5 across Tejon pass to connect Bakersfield to Los Angeles. The cost of the Palmdale route -- about $32 billion in current dollars -- is more than twice that of the direct link, and nobody wants to pay for it. The HSR project will be restricted to the Central Valley until the less expensive Tejon route is embraced.

Sunday, August 9, 2020

Currennt Financial Position for California HSR

Note: Financial data presented here (Tables 1-3) are drawn mainly from financial reports to the CHSR Finance & Audit Committee at its July 2020 meeting (scheduled but then canceled).

The California HSR project currently has enough money in the bank and in the pipeline from expected Prop 1A bond sales and Cap & Trade auctions that it isn't going to have a cash flow problem for at least five years. Its immediate problem is a slow pace of construction which is inadequate to meet established completion dates, particularly the Dec. 31, 2022, deadline for satisfying the federal funding agreement for completing the Central Valley Segment (Madera to Shafter). Work on thus segment has been underway for some five years, but it is only half completed with $5.2 billion expended so far and $6.5 B remaining in the budget (see Table 1). The current pace of construction is about $1 B per year (Table 2), so it is unrealistic to expect completion of the CVS before the end of 2025.

Current work on the CHSR Project includes construction of the CVS, a modest amount of work on the "bookends" (improvements to Caltrain and run-through tracks at LAUS), and completion of a full set of project-level EIRs for the entire Phase I, from San Francisco to Anaheim. CHSRA estimates the total cost of the current program at $14.7 B (Table 1), but adds "Other Costs" to reach a total of $15.6 B in the 2020 Draft Business Plan (Exhibit 3.4, p. 66). Some $6.7 B had been spent by May 31, 2020, according to the accounting in Table 1. About $8 B is budgeted to complete the current program, with a nominal completion date by the end of 2022 as specified by the federal Grant Agreement, but this deadline will not be met. CHSRA has only $2.6 B cash in hand (Table 3) with about $1.9 B expected from Cap & Trade, leaving it some $2.5 B short.

In 2019 Gov. Newsom set a specific goal for CHSR, to complete the entire CVS from Merced to Bakersfield (170 miles) before starting work on the Pachaco pass route to Gilroy and San Jose. The estimated cost for the entire CVS is $20.4 B (Business Plan, Exhibit 3.4), or $4.8 on top of the $8 B needed to complete the first 119 miles for a total remaining outlay of nearly $13 B to finish the entire CVS, from Merced to Bakersfield. Authorized funding throuh tht end of 2030 includes $2.6 B in the bank plus 10.5 years of Cap & Trade revenue at about $750 M per year, or $7.9 B, for a total of some $10.5 B. There is a $2.5 B shortfall, barring unexpected additional support.

What's the future for HSR in California?

The obvious short term goal is to complete the CVS (119 miles) without electrification, to fulfill the federal agreement; this would reduce travel time for the existing San Joaquin service by one-hour. The CHSRA appears committed to the North Initial Operational Segment (IOS), alias "Valley-to-Valley", from Bakersfield to San Jose, but this will require a major infusion of state funding which the legislature is unlikely to approve. The Early Train Operator (ETO) proposed completing the entire CVS (170 miles) including electrification, with diesel-powered feeder service from the north connecting to HSR at Merced. This would require an investment of some $10 B in additional funding in the San Joaquin and Altamont Corridor Express (ACE), including major improvement to Altamont Pass, to make it effective. IOS North is even more expensive, reqiring another $16 B in addition to the entire CVS.

The question of how to effectively use a stand-alone CVS -- either 119 or 170 miles -- is tied into the larger issue of the role HSR should play in expanding intercity rail service in California. The present State Rail Plan (2018) was prepared under the auspices of the previous Governor who was thoroughly committed to the current HSR Project, which depreciated the value of the existing corridors ("Amtrak California") and deferred major improvements to them until HSR Phase 1 was completed. Discussion of a better balanced plan will be covered in a subsequent post on this blog.

Table 1. Expended and Available Funds for California HSR

Author-ized Appropri-ated Program Budger Expended To Date Percent Expended
Project Development
Bond Fund (Prop 1A) $0.900 $0.575 $0.575 $0.494 86%
Cap and Trade $0.678 $0.678 $0.618 $0.160 26%
Federal Trust Fund (ARRA) $0.511 $0.511 $0.487 $0.487 100%
Subtotal, Project Develop. $2.089 $1.764 $1.681 $1.142 68%
Construction
Bond Fund (Prop 1A) $7.000 $2.609 $2.609 $2.4774 95%
Cap and Trade $10.498 $10.498 $7.037 $0.699 10%
Federal Trust Fund (ARRA) $2.1141 $2.114 $2.060 $2.060 100%
Subtotal, Construction $19.612 $15.221 $11.705 $5.235 45%
Bookend Projects (Local Assistance)
Bond Fund (Prop 1A) $1.100 $1.100 $1.100 $0.153 14%
Cap and Trade $0.198 $0.198 $0.198 $0.168 85%
Subtotal, Bookend Projects $1.2981 $1.298 $1.298 $0.320 25%
Subtotals by source of support
Bond Fund (Prop 1A) $9.000 $4.284 $4.284 $3.124 73%
Cap and Trade $11.374 $11.374 $7.853 $1.027 13%
Federal Trust Fund (ARRA) $2.625 $2.625 $2.547 $2.547 100%
TOTAL $22.999 $18.283 $14.684 $6.700 46%

Table 2. Cumulative Program Totals for California HSR

Total to 6/30 2014 FY 14-15 FY 15-16 FY 16-17 FY 17-18 FY 18-19 FY 19-20 Total to 6/30 2020
California Financial Support
Prop 1A $400 $45 $56 $1,323 $800 $600 $390 $3,614
Cap & Trade --- $650 $459 $221 $708 $787 $489 $3,313
Expenses by Category
Administrative $103 $17 $21 $22 $19 $21 $26 $229
Project Delivery $11 $8 $11 $13 $16 $17 $19 $94
Local Assist. --- --- --- --- $0 $92 $99 $191
Proj. Develop. $498 $46 $134 $179 $145 $86 $84 $1,171
Construction $227 $430 $879 $922 $1,016 $765 $1,400 $5,639
TOTAL $838 $501 $1,044 $1,135 $1,197 $981 $1,628 $7,325

Table 3. California Financial Support for HSR

Prop 1A Bond Fund Cap & Trade
Revenue $3,614 $3,313
Expenditures $3.124 $1.027
Difference, Revenue minus Expenditures $490 $2,286
Cash Balance, May 30, 2020 $288 $2,383