The current California HSR plan has significant flaws; a major mistake was selecting a detour via Palmdale instead of the direct route via I-5 across Tejon pass to connect Bakersfield to Los Angeles. The cost of the Palmdale route -- about $32 billion in current dollars -- is more than twice that of the direct link, and nobody wants to pay for it. The HSR project will be restricted to the Central Valley until the less expensive Tejon route is embraced.

Sunday, October 11, 2020

Cost overrun on Central Valley Segment?

The California HSR Project is facing a $1 billion cost overun on the Central Valley Segment (119 miles, Madera-to-Shafter), according to an article by Ralph Vartabedianin in the Los Angeles Times on Sept. 8, 2020. CHSR Authority financial reports provide limited information (see Table 1 below), and therefore provide little insight into the fraction of the project that has actually been constructed. Some 57% of the budgeted amount for the three design-build contracts had been expended by the end of July 2020, with no clue whether the project is actually within budget.

A more helpful source for gauging progress is the "Central Valley Status Report" which tracks how many structures and miles of guideway have been started, and how many completed, as summarized in Table 2 below. Counting projects underway as half complete on average, then guideway is 42% compete but structures are only 27% complete for the three constructions projects combined. This is discouraging: construction of the CVS is only one-third finished with less than 30 months before the December 2022 deadline. A cost overrun of $1 billion is likely, as Vartabedian indicates is his article in the Los Angeles Times. The CVS project has been beset by cost increases ("change orders") and delays involving substantial penalties.

Assuming that 80% of the Design-Build contracts, or $3.9 billion, is for actual construction, and two-thirds of that amount, or $2.6 billion, will be spent on the uncompleted projects, then the total expended on Design-Bulid will come to $5.4 billion, or about $500 million over budget. This is just a bit more than the $400 million paid to Tutor-Perini in delay penalties on CP-1 that Vartabedian reported, but this is not the only cost overrun he mentions. On the other hand, some projects have been completed within budget, such as the relocation of SR-99 in Fresno (not part of CP-1).

CP-1 (Madera to just south of Fresno) is particlarly complex, and the construction package most likely to incur a significant cost overrun. The section north of the San Joaquin River is well on the way to completion in the next two years, with six structures completed and construction on the remaining three overpasses now underway. The San Joaquin bridge is nearing completion, along with the viaduct and pergola over the UPRR tracks south of the bridge. The trench under SR 186 and the Cedar-Muscat viaduct are both in an advanced state of construction, and three overpasses (Ashlan Ave., Stanislaus St., and Tuolumne St.) are complete or nearly so. but construction has not even begun on at least three overcrossings and two undercrossings. Finally, relocation of four miles of Golden State Blvd. has just begun. By the HSR Authority's own count, construction is yet to start on 16 structures included in CP-1.

References

Table 1. Expenditures in the Central Valley as of July 31, 2020

Real Property Design-build
(Billion $)BudgetedExpendedPercentBudgetedExpendedPercent
CP1$0.817$0.74390.9%$2.250$1.27356.6%
CP2-3$0.534$0.37169.5%$2.035$1.14956.5%
CP4$0.184$0.14478.3%$0.594$0.35659.9%
Totals$1.535$1.25882.0%$4.879$2.77856.9%

Table 2. Progress on Construction in the Central Valley as of July 31, 2020

TotalAcquired, CompleteUnder WayRemain-ingPercent Complete
Right of Way (parcels)
CP11072832---24077.6%
CP2-31011645---36663.8%
CP4239163---7668.2%
Totals23221640---68270.6%
Structures (number)
CP1337101636.4%
CP2-3490202920.4%
CP41107431.8%
Totals937375127.4%
Guideway (miles)
CP1322111923.4%
CP2-36519262049.2%
CP421019.81.247.1%
Totals1182156.840.241.9%