Wednesday, May 7, 2014
How much HSR can be funded with Prop. 1A bonds?
The maximum high speed rail project that can be built using Prop. 1A bonds is limited to a cost of about $16.2 billion -- $8.1 billion allocated in the measure for HSR construction plus an equal amount in matching funds from other sources. The full Phase 1 defined in Prop. 1A (San Francisco to Anaheim) was expected to cost around $35 billion (according to the cost estimates included in the 2005 EIR), so Prop. 1A provided for an "initial operating segment" (IOS) that would provide the benefits of HSR over a shorter segment that could be built within the $16.2 billion cap inherent to Prop. 1A funding. The two options discussed in the 2012 Business Plan -- IOS-N (San Jose to Bakersfield) and IOS-S (Merced to San Fernando) -- price out to just about this cap, again using the construction costs estimated in the EIR.
The crucial issue of